A £10m contract was awarded to Clugston Construction to extend the campus. Portakabin was appointed to construct a £2m building using its off-site construction Portakabin Design and Build solution.
This new building comprised 52 steel-framed modules in two sizes, which were craned into position in just six days, reducing disruption and time on site by around 50 per cent.
Completed in only six months, the new two-storey 1,900m2 scheme replaced a number of older buildings with state-of-the-art modular buildings for schools, accommodating the Communications faculty for English and Modern Languages, and the Inclusion faculty. Alan Thomas, Architect at City of York Council, says: “The use of off-site construction gave us certainty of completion on time despite the challenging programme for the whole campus, and it allowed us to take this building off the critical path. It reduced time on site and disruption, allowing the adjacent sports centre to remain fully operational throughout the construction programme and ensuring the safety of the general public.”